DOĞABENDE EVLERİ
Start Date: January 2007
End Date: December 2008
LOCATION:
It is 150m away from the Palace of Justice in Bodrum.
It is located on the courthouse – Bodrum connection road and consists of offices for Lawyers and Financial Advisors.
PROJECT PLAN STRUCTURE:
4 Duplex Houses and
It consists of 12 offices for Lawyers, Financial Advisors, Architects, Engineers, and Doctors.
PROJECT CONTRACT DURATION:
Although it is a 2-year contract, it was completed and delivered within 1 year.
MATERIALS USED IN THE PROJECT:
- During the rough construction phase using the best brand products, the control of iron and concrete manufacturing was carried out by the technical application authority.
- Using “Bims Brick”, which provides thermal insulation in the wall productions of the project, stone sand plaster was applied on the exterior and Integrated gypsum plaster on the interior.
- During the concrete pouring, using the vibrator, cube samples were taken from ready-mixed concrete, and crushes were made in the laboratory of the concrete plant and it was tested whether the quality of the concrete complied with its class.
- At every stage of the manufacturing, the elevations are given in nivo.